## How to release SCM-Manager core (Script)
2020-05-08 16:35:16 +02:00
2023-01-26 20:00:27 +01:00
The most easy way to release the core is to use the release script. This will guide you
through all necessary tasks.
2020-03-09 08:01:43 +01:00
2023-01-26 20:00:27 +01:00
Mind that the script does not care about `support` branches, so if you have one, take
the manual way described below!
Make sure you have no changes you want to keep! The script will clean up everything.
```bash
./release.sh
```
It will
- Clean up your repository with the latest revision of `develop` ,
- Update the `CHANGELOG` file,
- Show you the changes it made,
- Ask you whether to proceed or not,
- Create a commit with the changes, and
- Create and push the release branch.
2024-09-17 13:58:36 +02:00
## Manual core release
2023-01-26 20:00:27 +01:00
2024-08-19 13:11:47 +02:00
To release a new version of SCM-Manager "manually", you have to do the following steps
2023-01-26 20:00:27 +01:00
(replace placeholders `<version>` accordingly, eg. with `2.1.0` ):
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Check out default branch
2020-03-09 08:01:43 +01:00
2020-03-13 15:44:35 +01:00
Make sure you have no changes you want to keep!
2020-03-09 08:01:43 +01:00
2023-01-26 20:00:27 +01:00
```bash
2020-06-04 19:06:16 +02:00
git fetch && git checkout -f origin/develop && git clean -fd && git checkout -B develop
2020-03-13 15:44:35 +01:00
```
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Merge support branch
2020-06-19 07:28:31 +02:00
Check whether there is an integration branch for the previous release or bugfixes not merged into the develop branch. Merge them now.
2023-01-26 20:00:27 +01:00
```bash
2020-06-19 07:28:31 +02:00
git merge origin/support/<support branch>
```
2024-09-17 13:58:36 +02:00
### Update Changelog
2020-03-09 08:01:43 +01:00
2021-02-02 11:02:31 +01:00
The changelog must be updated to reflect the changes for the new release.
All unreleased changes are stored in the `gradle/changelog` directory.
The changelog can be updated with the `updateChangelog` gradle task.
```bash
2023-01-26 20:00:27 +01:00
export VERSION=$(./gradlew :updateChangelog | grep -oP "Using next version \K[0-9.]+")
echo About to release version $VERSION
2021-02-02 11:02:31 +01:00
```
2023-01-26 20:00:27 +01:00
The update changelog task will tell you the next version number.
2021-02-02 11:02:31 +01:00
Now we should manually check if the changelog looks good.
```bash
git diff CHANGELOG.md
```
If everything looks fine, we can remove the changelog directory.
2024-09-17 13:58:36 +02:00
### Create release branch, commit changes and push
2020-03-09 08:01:43 +01:00
2021-02-02 11:02:31 +01:00
```bash
2022-01-21 15:58:19 +01:00
git rm -rf gradle/changelog \
&& git add CHANGELOG.md \
2023-01-26 20:00:27 +01:00
&& git checkout -b release/$VERSION \
2022-01-21 15:58:19 +01:00
&& git commit -m "Adjust changelog for release $VERSION" \
2025-04-03 14:55:08 +02:00
&& git push origin release/$VERSION \
&& xdg-open https://ecosystem.cloudogu.com/jenkins/view/SCMM/job/scm-manager/job/scm-manager/job/release%252F${VERSION}/
2021-02-02 11:02:31 +01:00
```
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Wait for Jenkins build
2020-03-09 08:01:43 +01:00
2020-03-13 15:44:35 +01:00
Jenkins will
2020-03-09 08:01:43 +01:00
2021-02-02 10:32:57 +01:00
- update `gradle.properties` and `package.json`
2020-03-13 15:44:35 +01:00
- merge with master branch
- build and deploy everything
- set the new development version for the develop branch
2020-04-09 19:45:24 +02:00
- delete the release branch
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Make a party
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
## Hotfix Releases of SCM-Manager
2023-03-13 08:32:29 +01:00
To release a hotfix version of SCM-Manager (or in other words a version, that is not based on the current
`develop` branch but on an older tag), there is a bit more manual work to do and there is no one-fits-all
way, so consider each step carefully and don't take this as a copy-paste manual like the normal release.
2024-09-17 13:58:36 +02:00
### Create hotfix branch
2023-03-13 08:32:29 +01:00
To trigger the release, create a hotfix branch on the tag you want to create the hotfix for (lets say,
that's version `2.30.0` ) and prepare the release like above:
```bash
git checkout 2.30.0
git checkout -b hotfix/2.30.1
```
Then apply your fixes (eg. by cherry picking the relevant commits) and update the `CHANGELOG.md` (if you
have single changelog yaml files, you could use the `updateChangelog` like above). Add the `CHANGELOG.md` ,
remove the yamls, and push the hotfix branch:
2025-03-12 15:07:49 +01:00
```bash
2023-03-13 08:32:29 +01:00
git rm -rf gradle/changelog
git add CHANGELOG.md
git commit -m "Adjust changelog for release 2.30.1"
git push origin hotfix/2.30.1
```
Jenkins will build and release the versions, create the new tag, but **will not ** update the `main` or
`develop` branches. So these updates come next.
2024-09-17 13:58:36 +02:00
### Update Branches
2023-03-13 08:32:29 +01:00
Depending on whether you released a hotfix for an older version or the latest release, you have to update
the `main` branch to the new tag. So in our example, if there is no version `2.31.x` yet, the new version
`2.30.1` is the latest version and we have to update `main` :
2025-03-12 15:07:49 +01:00
```bash
2023-03-13 08:32:29 +01:00
git checkout main
git merge 2.30.1
git push origin main
```
Regardless of the `main` branch, you should update the `develop` branch and merge the hotfix to make clear,
that there are no changes that all changes are part of the current `develop` state. Normally, this leads
to merge conflicts, because the version on `develop` has been set to a new `SNAPSHOT` , while the version
of the hotfix has been updated to the new release version. So you have to merge all these conflicts manually.
2025-03-12 15:07:49 +01:00
```bash
2023-03-13 08:32:29 +01:00
git checkout develop
2023-09-01 11:10:43 +02:00
git merge main
2023-03-13 08:32:29 +01:00
```
How these conflicts should be merged depends on the version that has been released:
- If it has been a hotfix for an older version, you could keep the SNAPSHOT versions and simply discard the
released version.
- If the hotfix is the new main, you should take this new version and then manually create a new SNAPSHOT
based on the new hotfix version number using gradle: `./gradlew setVersionToNextSnapshot` .
2024-09-17 13:58:36 +02:00
## How to release SCM-Manager plugins
2020-03-09 08:01:43 +01:00
2024-08-19 13:11:47 +02:00
To release a new version of a Plugin for SCM-Manager you have to do the following steps (replace placeholder `<version>` accordingly, eg. with `2.1.0` ):
2021-02-02 10:32:57 +01:00
2024-09-17 13:58:36 +02:00
### Check out default branch
2020-03-13 15:30:52 +01:00
2020-03-13 15:44:35 +01:00
Make sure you have no changes you want to keep!
2020-03-13 15:30:52 +01:00
2023-01-26 20:00:27 +01:00
```bash
2020-06-04 19:06:16 +02:00
git fetch && git checkout -f origin/develop && git clean -fd && git checkout -B develop
2020-03-13 15:30:52 +01:00
```
2024-09-17 13:58:36 +02:00
### Merge support branch
2020-06-19 07:28:31 +02:00
Check whether there is an integration branch for the previous release or bugfixes not merged into the develop branch. Merge them now.
2023-01-26 20:00:27 +01:00
```bash
2020-06-19 07:28:31 +02:00
git merge origin/support/<support branch>
```
2024-09-17 13:58:36 +02:00
### Update SCM parent if necessary
2020-03-09 08:01:43 +01:00
2020-04-14 15:37:18 +02:00
If you need to update the parent of the plugin to a new release of SCM-Manager, change it now:
2020-03-09 08:01:43 +01:00
2021-02-02 10:32:57 +01:00
- `build.gradle` : `scmVersion`
2020-04-14 15:37:18 +02:00
- `package.json` : `dependencies.ui-plugins`
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Plugin dependencies
2020-06-18 14:50:28 +02:00
Check if all plugin dependencies are proper versions and not SNAPSHOT!
2024-09-17 13:58:36 +02:00
### Build, commit and push
2020-06-18 14:50:28 +02:00
2023-01-26 20:00:27 +01:00
This step is only needed, when you had to update the version in the prior step.
If the core version has not been increased, this step can be skipped.
```bash
2021-02-02 10:32:57 +01:00
./gradlew build \
&& git add yarn.lock build.gradle package.json \
2020-06-04 19:06:16 +02:00
&& git commit -m "Update to new version of SCM-Manager" \
2020-06-04 20:10:19 +02:00
&& git push origin develop
2020-04-14 15:37:18 +02:00
```
2020-03-09 08:01:43 +01:00
2020-04-14 15:37:18 +02:00
Wait for Jenkins to be green.
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Update Changelog
2021-11-04 09:39:41 +01:00
The changelog must be updated to reflect the changes for the new release.
All unreleased changes are stored in the `gradle/changelog` directory.
The changelog can be updated with the `updateChangelog` gradle task.
```bash
2023-01-26 20:00:27 +01:00
export VERSION=$(./gradlew :updateChangelog | grep -oP "Using next version \K[0-9.]+")
echo About to release version $VERSION
2021-11-04 09:39:41 +01:00
```
2023-01-26 20:00:27 +01:00
The task will tell you the next version number.
2021-11-04 09:39:41 +01:00
Now we should manually check if the changelog looks good.
```bash
git diff CHANGELOG.md
```
2020-04-14 15:37:18 +02:00
2024-09-17 13:58:36 +02:00
### Create, commit and push release branch
2020-03-09 08:01:43 +01:00
2023-01-26 20:00:27 +01:00
This step needs the `VERSION` set in the step above.
```bash
git rm -rf gradle/changelog \
&& git add CHANGELOG.md \
2020-06-04 20:10:19 +02:00
&& git checkout -b release/$VERSION \
2023-01-26 20:00:27 +01:00
&& git commit -m "Prepare release of $VERSION" \
2025-04-03 14:55:08 +02:00
&& git push origin release/$VERSION \
&& xdg-open https://ecosystem.cloudogu.com/jenkins/view/SCMM/job/scm-manager-plugins/job/$(basename $(pwd))/job/release%252F${VERSION}/
2020-03-09 08:01:43 +01:00
```
2024-09-17 13:58:36 +02:00
### Wait for Jenkins build
2020-03-09 08:01:43 +01:00
2020-04-09 19:45:24 +02:00
Jenkins will
2020-03-09 08:01:43 +01:00
2021-02-02 10:32:57 +01:00
- update versions in gradle.properties and package.json
2020-04-09 19:45:24 +02:00
- merge with master branch
- build and deploy everything
- set the new development version for the develop branch
- delete the release branch
2020-03-09 08:01:43 +01:00
2024-09-17 13:58:36 +02:00
### Attention: Creating new plugins
2021-02-02 10:32:57 +01:00
If you are creating a new plugin which doesn't exist in the SCM-Manager Plugin-Center yet, your plugin will not be shown after the release.
First you have to create a `plugin.yml` in the website repository.
2020-03-31 18:29:36 +02:00
2020-10-09 13:10:53 +02:00
Example: https://github.com/scm-manager/website/blob/master/content/plugins/scm-teamscale-plugin/plugin.yml
2022-10-12 11:52:12 +02:00
2024-09-17 13:58:36 +02:00
### Hotfix Release
2022-10-12 11:52:12 +02:00
The release of a hotfix version is still a partly manual process that requires some knowledge
of git and the versioning of SCM-Manager. Here is a helping hand as a guideline of how to release
a bugfix version of the latest release (for example a 2.x.1 after 2.x.0 has been released).
Mind that this process is only necessary, when there are commits on `develop` that shall **not ** be
released, yet.
2024-11-05 16:27:30 +01:00
1. Checkout the tag of the release you want to create a bugfix release for (`git checkout <version to fix>` )
2. Create a hotfix branch for the new version (`git checkout -b hotfix/<new version>` )
2022-10-12 11:52:12 +02:00
3. Apply the changes upon this branch
2024-11-05 16:27:30 +01:00
4. Create the changelog either manually or by running `./gradlew :updateChangelog`
5. Delete the changelog yaml files and add the `CHANGELOG.md` (`git rm -rf gradle/changelog && git add CHANGELOG.md` )
6. Double check this all
7. Commit the changes and push the hotfix branch
8. Jenkins will build and release this hotfix with the given version
2025-05-20 10:36:08 +02:00
**Important Note:**
After the first successful run, a second will start and always fail.
This is due to the pipeline updating the tag version and commit / pushing this change to the hotfix branch.
This second build will always fail, but this second build has no impact on whether the release has been successful or not.
2024-11-05 16:27:30 +01:00
9. When Jenkins has finished, fetch the changes (and the new tag)
10. Merge this new Tag into `main` (or fast-forward `main` if possible) and push `main`
(`git checkout main && git pull && git merge hotfix/<new version> && git push` )
11. Merge this commit into `develop` and resolve the conflicts
12. If the hotfix is based upon the latest release, set the version to the next snapshot (`./gradlew setVersionToNextSnapshot && ./gradlew fix` ) and commit these changes
2022-10-12 11:52:12 +02:00
If the hotfix has been created for an older release, this process might be somewhat more complicated.